How Long Does It Take to Renovate or Rebuild a Landed House in Singapore?
One of the most common questions homeowners ask at the start of a project is:
“How long will everything take?”
While each project is different, understanding the typical stages of a residential project can help set realistic expectations.
1. Feasibility and Concept Design
Estimated duration: 1–2 months
This early stage studies the site, planning constraints, and potential design approaches.
It allows homeowners to understand:
What is possible on the site
Whether A&A or rebuilding makes more sense
Approximate construction scale
2. Design Development
Estimated duration: 2–3 months
During this stage the design is refined and coordinated with structural and engineering requirements.
Key decisions include:
Internal layouts
Building form
Materials and façade design
3. Authority Submissions
Estimated duration: 3–4 months
Residential projects typically require approvals from authorities such as:
Urban Redevelopment Authority
Building and Construction Authority
Singapore Civil Defence Force
Approval timelines depend on the complexity of the proposal.
4. Tender and Contractor Appointment
Estimated duration: 2-3 months
During this stage the design is priced by contractors and the construction team is finalised.
5. Construction
Typical durations:
A&A projects : 9–12 months
Rebuild projects : 15–24 months
Actual timelines vary depending on project complexity and site conditions.
Final Thoughts
Residential projects require coordination between design, authorities, and construction. Planning the timeline early allows homeowners to manage expectations and make better decisions during the design process.